62 agreements, 31 of them within ninety days. Every date below is written as a date in a sentence that imposes an obligation — quoted here, with the page it sits on.
| Due | Entity and the sentence that binds it | Filed by | Remedy | Page |
|---|---|---|---|---|
| 31 Oct 2026 | Cosupply, LLC, d/b/a C&O SupplyA Certificate of Occupancy shall be obtained and the Facility opened no later than October 31, 2026 | Grapevine | repayment | 4 |
| 30 Dec 2026 | ARIJI BESS, LLCOwner covenants and agrees to achieve commencement of commercial operations (hereinafter referred to as “COD”) by no later than December 30, 2026 | Howard | repayment | 4 |
| 31 Dec 2026 | MAGNOLIA RE, LLCMAGNOLIA shall create, fill, and retain at least 75 new full-time jobs that are WMCEDC eligible (“New Jobs”) at the Facility on or before December 31, 2026. | McLennan | repayment | 3 |
| 31 Dec 2026 | Walmart Inc.Except in cases of force majeure, Business shall complete the Project by December 31, 2026. | McLennan | unclear | 2 |
| 31 Dec 2026 | Westlake Pipe and Fittings CorporationThe capital investments related to the Real Property contemplated by this Article must be completed on or before December 31, 2026, subject to Force Majeure. | Wichita | termination no repayment stated | 6 |
| 31 Dec 2026 | Solar Star North Herty Storage, LLCa. Owner/Grantee agrees to invest a minimum of Eighty Million Dollars ($80,000,000.00) in the Project, to add, improve, modernize, upgrade or renovate the Real and tangible Personal Property at its Facility, and to begin operation of the Fa | Angelina | repayment | 4 |
| 31 Dec 2026 | Equinox Hotel Arlington, LPOWNER shall complete the Conference Space Improvements by no later than December 31. 2026. | Arlington | repayment discretionary | 5 |
| 31 Dec 2026 | H-E-B, LPHEB shall construct the Grocery Store and open the Grocery Store to the public for business on or before December 31, 2026 (the “Opening Deadline”). | Euless | none stated only the statutory immigration clause | 4 |
| 31 Dec 2026 | Spectrum Gulf Coast LLCFinal Completion of the Broadband Project shall occur no later than December 31, 2026, no exceptions unless mutually agreed upon. | El Paso | unclear | 2 |
| 31 Dec 2026 | River Hills LLCCompany shall cause the Capital Investment on the Property to be not less than $4,000,000 on or before December 31, 2026. | Kerrville | repayment | 9 |
| 31 Dec 2026 | LF Gateway LPCompany shall construct and complete on or before either December 31, 2026 | Mesquite | unclear | 16 |
| 31 Dec 2026 | H-E-B, LPHEB shall construct the Grocery Store and open the Grocery Store to the public for business on or before December 31, 2026 (the “Opening Deadline”). | Bedford | repayment | 4 |
| 31 Dec 2026 | Reynolds Presto Products Inc.The Expansion and Improvements shall occur by December 31, 2026. | Carrollton | repayment | 5 |
| 31 Dec 2026 | AER Manufacturing, LPThe Expansion and Improvements shall occur by December 31, 2026. | Carrollton | repayment | 5 |
| 31 Dec 2026 | 3MEBS PROPERTY COMPANY, LLCNo later than December 31, 2026, Company must receive final inspection and approval of the Public Improvements | Bedford | repayment | 5 |
| 31 Dec 2026 | UEP, Inc.Phase 1 (a) Real Property Improvements. The Company shall construct Improvements having a minimum Construction Cost of Seven Million Dollars ($7,000,000). (b) | Commencement of Improvements. The Expansion and Improvements shall occur by Dec | Carrollton | repayment | 6 |
| 31 Dec 2026 | ARLINGTON ECONOMIC DEVELOPMENT CORPORATIONThe AEDC shall complete the project no later than December 31, 2026. | Arlington | none stated | 2 |
| 31 Dec 2026 | ATWOOD DISTRIBUTING LPOn or before December 31, 2026, the Company shall create and maintain at least thirty-two (32) Full-Time Equivalent Jobs | Palestine | repayment | 4 |
| 31 Dec 2026 | Zenner USA, Inc.Company obligations to perform under this Agreement shall be completed by December 31, 2026. | Huntsville | repayment | 4 |
| 31 Dec 2026 | BENRHXX, LLCCompany shall use commercially reasonable efforts to obtain the Certificate of Occupancy on or before December 31, 2026 | North Richland Hills | none stated | 2 |
| 31 Dec 2026 | Providence Equipment, LLCCompletion of Construction shall occur on or before December 31, 2026. | Kemp | repayment | 8 |
| 31 Dec 2026 | ONU VENTURES, INC.Developer/Grantee must complete the Project Components described in Section 5.C. on or before December 31, 2026 (the "Substantial Completion Deadline") | Dallas | repayment | 5 |
| 31 Dec 2026 | Delta Millworks Holdings, LLC, a Texas Limited Liability Corporation, and Delta Hays Holdings, LLC, a Texas Limited Liability CorporationDelta shall have until December 31, 2026 to complete construction as set forth in Article III below. | Hays | none stated | 4 |
| 31 Dec 2026 | Shoppes at Crown Point, LLCGrantee agrees to construct the Improvements described at the location stated on Exhibit A hereto on or before December 31, 2026. | North Richland Hills | repayment | 2 |
| 31 Dec 2026 | ENVASES COMMERCE, LLC AND IZ TEXAS, LLCOn or before December 31, 2026, the Companies shall invest at the Premises no less than One Hundred and Seventeen Million Six Hundred Thousand Dollars ($117,600,000.00) | McLennan | unclear | 4 |
| 31 Dec 2026 | Sandlin Homes, LLCGrantee agrees to construct the Improvements described at the location stated on Exhibit A hereto on or before December 31, 2026. | North Richland Hills | repayment | 2 |
| 31 Dec 2026 | CURT MANUFACTURING, LLCThe Employer shall obtain a Certificate of Occupancy no later than December 31, 2026. | Guadalupe | none stated | 6 |
| 31 Dec 2026 | Sonoma Trail Partners, Ltd.On or before December 31, 2026 (“Completion Deadline”), Developer shall Complete (as hereinafter defined) all of the Work at Developer’s cost. | Ennis | none stated | 3 |
| 01 Jan 2027 | Lineage Logistics, LLCIn no case shall Year 1 begin later than January 1, 2027. | Laredo | repayment | 3 |
| 01 Jan 2027 | MIWD Holding Company, LLCNo later than January 1, 2027, the Company shall target to employ at least seven hundred (700) FTEs at the Facility. | Flower Mound | repayment | 5 |
| 20 Jan 2027 | 2049 Cinema Drive, LLCDeveloper shall obtain a certificate of occupancy for the retail development on the Property by January 20, 2027. | Hudson Oaks | none stated | 3 |
| 31 Jan 2027 | Lowe’s Homes Center, LLCDeveloper agrees to commence operations as a retail store open to the public by January 31, 2027 | Kaufman | unclear | 5 |
| 01 Mar 2027 | BIG D LUMBER COMPANY, LLCCompany covenants and agrees to obtain or maintain a City Certificate of Occupancy for the Facility located on the Property on or before March 1, 2027 | Van Alstyne | repayment | 5 |
| 01 Mar 2027 | SAF CTP, LLCCompany shall, subject to delays caused by events of Force Majeure, cause Completion of Construction of the Tenant Improvements to occur on or before March 1, 2027. | Richardson | repayment | 5 |
| 31 Mar 2027 | CONVERGENCE CAPITAL, LLCCompany shall use commercially reasonable efforts to obtain the Certificate of Occupancy on or before March 31, 2027 | North Richland Hills | repayment | 2 |
| 31 Mar 2027 | Nack Development, LLCNo later than March 31, 2027, Company must receive a Building Final for Phase 1 Improvements | Mansfield | none stated | 2 |
| 01 Apr 2027 | DD Gateway Village, Ltd.No later than April 1, 2027, Company must cause Final Completion of the Improvements to occur | Bedford | repayment | 6 |
| 31 May 2027 | Sabal Market Center, LLCCompany's obligations to perform under this Agreement shall be completed by May 31, 2027. | Brownsville | unclear | 9 |
| 31 May 2027 | 108 N MAIN, LLCCompany shall complete the Required Improvements and shall obtain its final Certificate of Occupancy for the Project and be open for business on or before May 31, 2027 | Buda | repayment | 7 |
| 31 May 2027 | 108 N MAIN, LLCCompany shall complete the Required Improvements and shall obtain 1ts final Certificate of Occupancy for the Project and be open for business on or before May 31, 2027 | Buda | repayment | 7 |
| 01 Jun 2027 | Sally Holdings LLCCompany shall submit its Initial Grant Request to the City after 180 days of actual Occupancy and not later than June 1, 2027. | Plano | repayment | 5 |
| 01 Jun 2027 | T&J DFW Properties LLCDeveloper shall obtain a certificate of occupancy for the Project not later than June 1, 2027. | Pilot Point | none stated only the statutory immigration clause | 2 |
| 15 Jun 2027 | JP Analytical LLC.Company shall create and fill, not less than five (5) Employment Positions at the Leased Premises on or before June 15, 2027 | Richardson | repayment | 5 |
| 30 Jun 2027 | CLEAR CHOICE HOSPITAL, LLCbut in no case shall Year | begin later than June 30, 2027. | Laredo | repayment | 3 |
| 07 Jul 2027 | Robert Kyle Gabhart of Bluegrass Legacy Groupby July 7, 2027, the Completion Date, Grantee shall have completed the Grant application | Keller | repayment | 3 |
| 31 Jul 2027 | Victoria Exchange Development, LPDeveloper agrees that the above-described construction to include Phase I and Phase II shall be completed, including all items as described in Sections 1-3 above, on or before July 31, 2027, in order to receive reimbursement as described in | Victoria | repayment | 3 |
| 31 Aug 2027 | Mint Transportation LLCGrantee agrees to construct the improvements shown and described on Exhibit A to final 100% completion with no punch-list items remaining on or before August 31, 2027 | North Richland Hills | repayment | 3 |
| 30 Sep 2027 | DOCTORS HOSPITAL AT RENAISSANCE, LTD. dba DHR Health BrownsvilleCompany's obligations to perform under this Agreement shall be completed by September 30, 2027. | Brownsville | unclear | 8 |
| 31 Dec 2027 | Montgomery County Municipal Utility District No. 118The Road Improvements Completion Date shall be no later than December 31, 2027, unless otherwise agreed to by the County. | Montgomery | none stated | 2 |
| 31 Dec 2027 | Schneider Electric USA, Inc.Failure of the Company to obtain a permanent Certificate of Occupancy for the Development by December 31, 2027 shall result in the immediate termination of this Agreement | El Paso | repayment discretionary | 6 |
| 31 Dec 2027 | Schneider Electric USA, Inc.Failure of the Applicant to obtain a permanent Certificate of Occupancy for the Development by December 31, 2027 shall result in the immediate termination of this Agreement | El Paso | repayment | 6 |
| 31 Dec 2027 | PR Gypsum, LLCby December 31, 2027, Grantee shall have made a capital investment in tangible personal property | Denton | repayment | 9 |
| 31 Dec 2027 | RRTX Lake Creek Hotel, L.P.LCH agrees to spend a cumulative total of at least $2,650,000.00 in improvements to the Property no later than December 31, 2027. | Round Rock | repayment | 3 |
| 31 Dec 2027 | 5307 Broadway, Ltd.Ridgemont shall complete construction of the Project and open at least one of the planned restaurants for business to the public on or before December 31, 2027. | Alamo Heights | repayment | 4 |
| 31 Dec 2027 | FormFactor, Inc.the Project shall be fully operational by December 31, 2027 | Farmers Branch | termination no repayment stated | 12 |
| 31 Dec 2027 | Midland Downtown Renaissance, LPNotwithstanding the foregoing paragraph or any contrary provision contained herein, MDR shall satisfy the Financing Obligation on or before December 31, 2027. | Midland | repayment | 9 |
| 31 Dec 2027 | Texas Roadhouse of Baytown, TX LLC and Strategic Restaurant Enterprises, Inc.in no event shall be later than December 31, 2027. | Baytown | termination no repayment stated | 2 |
| 31 Dec 2027 | Mayday Manufacturing Co.by December 31, 2027, Grantee shall have made the Improvements on the Premises which result in a combined assessed valuation of the improvements and tangible personal property (excluding inventory, vehicles, and supplies) on the Premises of | Denton | none stated only the statutory immigration clause | 8 |
| 01 Jan 2028 | The Kate WF, LLC.The capital investments related to the Personal Property contemplated by this Paragraph 3.02 must be completed on or before January 1, 2028, subject to Force Majeure. | Wichita | repayment | 6 |
| 01 Jan 2028 | KILLAM DEVELOPMENT, LTD.the Company shall make a cumulative investment of not less than $4,000,000 in the Improvements described in Article III of this Agreement by no later than January 1, 2028 | Laredo | repayment | 8 |
| 01 Jan 2028 | Champion Equity Holdings, LLCDeveloper shall obtain a certificate of occupancy for the Project not later than January 1, 2028. | Pilot Point | repayment | 2 |
| 31 Jan 2028 | BALCH SPRINGS ALEXANDER, LLCDeveloper covenants and agrees to provide to the other Parties said invoices or other documentation for the Qualified Expenditures by January 31, 2028. | Balch Springs | repayment | 6 |
They state a period from an event — twenty-four (24) calendar months after the City approval
, ninety (90) days after Commencement
. The approval date is not in the registry, so there is no honest way to put those on a calendar. They are not estimated here.
Also excluded: dates that appear only in a definition, dates a contract’s own quoted sentence does not support, and residential grant programmes.
Including the ones above that state a period rather than a date — those I work out by hand, with both documents open, and show you the arithmetic.