Agreement 0012382, filed with the Texas Comptroller by City of Mansfield, Texas.
Where a deadline above has passed, no public record exists of whether it was met — not in the Comptroller’s filings, nor in the local government’s own disclosures. That is not evidence of non-compliance. Texas requires nobody to record it.
A local abatement waives only that taxing unit’s share of the property tax bill. School districts, counties, cities and hospital districts each sign separately.
| Field | Value & quoted source | Page |
|---|---|---|
| Granting body | City of Mansfield, TexasCity of Mansfield, Texas, a home-rule municipal corporation located tn Tarrant, Johnson and Ellis Counties, Texas (the “City”), Mansfield Economic Development Corporation, a 4A Economic Development Corporation (the “MEDC”) | 3 |
| Contracting entity | Zah Group, Inc.Zah Group, Inc., a Delaware corporation authorized to conduct business in Texas (“Company”) | 3 |
| Parent / guarantor | Klein Toolscapital expansion of the existing Klein Tools owned facilities in Mansfield, Texas | 4 |
| Instrument | Economic Incentive and Performance AgreementThis Economic Incentive and Performance Agreement (“Agreement”) | 3 |
| Governing chapter | Chapter 380, Local Government Codeand WHEREAS, under the authority granted by Article III, Section 52-a of the Texas Constitution and Chapter 380 of the Texas Local Government Code, the City is authorized to provide additional economic development incentives to promote local economic development and stimulate business and commercial activity; | — |
| Capital investment | $75,000,000Real Property Improvements $75,000,000 | 18 |
| Grant or incentive | $17,500,000$ 2,500,000 $15,000,000 $17,500,000 | 20 |
| Jobs committed | 400 the quoted sentence states no obligationthe creation of 400 additional full-time jobs over a ten-year period | 4 |
| Wage requirement | $75,000.00with at least 100 FTEs with an average salary of $75,000.00 | 19 |
| Square footage | 585,000125,000 square feet Class A Office Space facility for its Global Research and Development Headquarters; an estimated 460,000 square foot warehouse facility | 4 |
| Acreage | Not stated in the agreement | — |
| Performance deadline | October 31, 2028Certificate of Occupancy. The phrase “Certificate of Occupancy” shal! mean a Final Certificate of Occupancy issued by the City’s Building Safety Department to the Company for the Project and must be obtained by the Company not later than October 31, 2028. | 5 |
| Expiration | December 30, 2043Expiration Date. The phrase “Expiration Date” shall mean December 30, 2043. | 5 |
| Effective date | July 15, 2025EXECUTED to be effective the (S day of Duly , 2025. | 17 |
| Signatory | Thomas Klein Sr.Thomas Klein Sr., Chairman / CEO | 15 |
| Chain status | Superseded by agreement 0013439 | — |
125,000 square feet Class A office space facility for their Global Research and Development Headquarters; construction of an additional estimated 460,000 square foot warehouse
Agreement 0012382 is filed with the Texas Comptroller. Pull the PDF, go to the page number beside any row, and read the sentence. If a figure here does not match the document, tell me and it is corrected the same day.
Where the contract says nothing, the field is left empty rather than filled with a guess.
This is a single agreement. I have read 1,645 of the 4,428 Texas has filed, resolved which have been superseded, and recorded what each commits a company to.
Send me an entity and a county and I will tell you what is on it — quoted, page-cited, checked. Free for the first one.