Agreement 0002409, filed with the Texas Comptroller by Polk County, Texas.
Where a deadline above has passed, no public record exists of whether it was met — not in the Comptroller’s filings, nor in the local government’s own disclosures. That is not evidence of non-compliance. Texas requires nobody to record it.
A local abatement waives only that taxing unit’s share of the property tax bill. School districts, counties, cities and hospital districts each sign separately.
| Field | Value & quoted source | Page |
|---|---|---|
| Granting body | Polk County, TexasTHIS TAX ABATEMENT AGREEMENT (the “Agreement’), effective as of the last date set forth on the signature page hereto (the “Effective Date”), is made and entered into by and between Polk County, Texas, (“County”), acting through its duly elected officers and Umbriel Solar, LLC | 2 |
| Contracting entity | Umbriel Solar, LLCTHIS TAX ABATEMENT AGREEMENT (the “Agreement’), effective as of the last date set forth on the signature page hereto (the “Effective Date”), is made and entered into by and between Polk County, Texas, (“County”), acting through its duly elected officers and Umbriel Solar, LLC | 2 |
| Parent / guarantor | Not stated in the agreement | — |
| Instrument | Tax Abatement AgreementTAX ABATEMENT AGREEMENT | 1 |
| Governing chapter | Chapter 312, Tax Code (property tax abatement)and all other tangible personal property permitted by Chapter 312 of the Texas Tax Code and the Guidelines & Criteria. | — |
| Capital investment | $135,000,000.00With the construction of the Project, UMBRIEL will invest an amount estimated to be one hundred thirty-five million and zero one hundredths dollars ($135,000,000.00) in the Improvements and control (acquisition or lease) of the Site for the Business Activities | 5 |
| Grant or incentive | Not stated in the agreement | — |
| Jobs committed | 1 recital language, not a covenantUMBRIEL covenants and agrees if it constructs the Project at the Site to create and maintain throughout the Term of this Agreement no fewer than one (1) new permanent jobs to work at and support the Project’s facility | 9 |
| Wage requirement | $41,823shall be paid no less than approximately forty-one thousand eight hundred twenty-three dollars ($41,823) per year | 9 |
| Square footage | Not stated in the agreement | — |
| Acreage | 5.939.349Total Acres: 5.939.349 | 41 |
| Performance deadline | December 31, 2023UMBRIEL agrees to use commercially reasonable efforts to construct and to install the Project and provide the Certificate to County no later than December 31, 2023 (the “Completion Deadline”). | 10 |
| Expiration | Not stated in the agreement | — |
| Effective date | November 10, 2020Date: November 10, 2020 | 20 |
| Signatory | Michael U.Name: Michael U. =a | 20 |
| Chain status | Terminal document — no later agreement in the registry names this one as its predecessor | — |
1) Solar modules/panels 2) Steel/aluminum/other metal mounting system with tracking capabilities 3) Underground conduit, communication cables, and electrical collection system wiring 4) Multiple combiner boxes 5) One or multiple project substation(s) including breakers, a transformer, and meters 6) Collection substation will be connected to utility interconnection by an above ground transmission line 7) Inverter boxes on concrete or gravel pads 8) Operations and maintenance facility 9) Fencing for safety and security 10) Telephone system 11) New or improved access and service roads 12) Meteorological equipment to measure solar irradiation and weather conditions
Agreement 0002409 is filed with the Texas Comptroller. Pull the PDF, go to the page number beside any row, and read the sentence. If a figure here does not match the document, tell me and it is corrected the same day.
Where the contract says nothing, the field is left empty rather than filled with a guess.
This is a single agreement. I have read 1,645 of the 4,428 Texas has filed, resolved which have been superseded, and recorded what each commits a company to.
Send me an entity and a county and I will tell you what is on it — quoted, page-cited, checked. Free for the first one.